Contents
Executive Summary
1.1
Purpose of the
Report
1.2
Structure of the
Report
2.1
Background
2.2
General Site
Description
2.3
Construction
Activities
2.4
Project
Organisation and Management Structure
2.5
Status of
Environmental Approval Documents
3
Environmental Monitoring
Requirements, environmental Mitigation Measures
4
Implementation Status on Environmental Protection
Requirements
6.1
Weekly Site
Audits
6.2
Landscape and
Visual Audit
7
Environmental Non-conformance
7.1
Summary of
Environmental Non-Compliance
7.2
Summary of
Environmental Complaint
7.3
Summary of
Environmental Summon and Successful Prosecution
8.1
Key Issues for
the Coming Month
8.2
Construction
Programme
LIST OF TABLES
Table
2.1 Summary of Construction Activities Undertaken
in the Reporting Period
Table
2.2 Summary of Environmental Licensing,
Notification and Permit Status
Table
5.1 Quantities of Waste Generated from the
Project
Table
8.1 Construction Works to be undertaken in the
Next Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
Environmental complaint, Environmental Summons and Prosecution Log |
Annex h |
|
|
|
EXECUTIVE SUMMARY
The construction works of No.
EP/SP/61/10 Organic Resources Recovery Centre Phase 1 (the
Project) commenced on 21
May 2015. This is the 44th
monthly Environmental Monitoring and Audit (EM&A) report presenting the
EM&A works carried out during the period from 1 to 31 January 2019 in
accordance with the EM&A Manual.
Summary of
Construction Works undertaken during the Reporting Month
Works undertaken in the reporting
month included:
·
Systems
being operated – waste reception, pre-treatment, CAPCS extraction, the
digesters, the centrifuge, the desulphurisation, the emergency flare, the CHPs,
the ASP and the biological wastewater treatment plant; and
·
Process
commissioning in progress, operations included waste reception, pre-treatment,
CAPCS extraction, the digesters, the centrifuge, the composting tunnels, the
desulphurisation, the emergency flare, the CHPs, the ASP and the biological
waste water treatment plant (about 110-130t/d SSOW input).
Environmental
Monitoring and Audit Progress
A summary of the monitoring activities undertaken in
this reporting period is listed below:
·
Joint Environmental Site Inspections |
4
times |
·
Landscape & Visual Inspections |
2
times |
Odour
Odour patrol were conducted by
representatives of the Contractor, the ER and Employer (EPD Project Team) on 2,
4, 7, 9, 11, 14, 16, 18, 21, 24, 25, 28 and 30 January 2019. No Level 2 Odour Intensity was recorded during
odour patrols.
No air sample was collected during
this reporting period.
Waste Management
Waste generated from this Project
includes inert construction and demolition (C&D) materials (public fill)
and non-inert C&D materials (construction wastes).
Inert C&D materials (public
fill) include bricks, concrete, building debris, rubble and excavated spoil. In
total, 21.13 tonnes of inert C&D material were generated from the Project.
Non-inert C&D materials
(construction wastes) include metals, paper / cardboard packaging waste,
plastics and other wastes such as general refuse. 0.00 kg of metals, 0.00 kg of papers/
cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling
during the reporting period. 4.55 tonnes
of general refuse was disposed of at the landfill.
1,880.00 L of chemical waste was
collected by licenced waste collector.
Environmental
Site Inspection
Four
weekly joint environmental site inspections were carried out by the
representatives of the Contractor, ER, IC and the ET. The
IEC was also present at the joint inspection on 17 January
2019. Details of the audit findings and
implementation status of the mitigation measures are presented in Section
6.1.
Landscape &
Visual
On-site inspections on landscape
and visual mitigation measures were performed on 8 and 25 January 2019. Details of the audit findings and
implementation status of the mitigation measures are presented in Sections
6.2.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance was recorded during
the reporting period.
No incident occurred during the
reporting period.
No complaint/summon/prosecution was
received in this reporting period.
Future Key
Issues
Works to be undertaken in the next
reporting month include:
·
Continue testing and process commissioning works.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which
the project name has been updated to Organic Resources Recovery Centre
(Phase I) (the Project) since November 2017.
This is the 44th EM&A report which
summarises the monitoring results and audit findings for the EM&A programme
during the reporting period from 1 to 31 January 2019.
The structure of the report is as follows:
Section 1: Introduction
It details the scope and structure of the report.
Section 2: Project Information
It summarises the
background and scope of the Project, site description, project organization,
construction programme, construction works undertaken and status of the
Environmental Permits (EP)/licences over the construction phase of the Project.
Section 3: Environmental
Monitoring Requirements
It summarises the environmental monitoring
requirements including monitoring parameters, programmes, methodologies,
frequency, locations, Action and Limit Levels, Event/Action Plans,
environmental mitigation measures as recommended in the EM&A Manual and
approved EIA report.
Section 4: Implementation
Status on Environmental Mitigation Measures
It summarises the implementation of environmental
protection measures during the reporting period.
Section 5: Waste Management
It summarises the quantity of public fill and
construction waste generated in the reporting period
Section 6: Environmental Site
Inspection
It summarises the audit findings of the weekly site
inspections undertaken within the reporting period.
Section 7: Environmental
Non-conformance
It summarises any exceedance of environmental
performance standard, environmental complaints and summons received within the
reporting period.
Section 8: Further
Key Issues
It summarises the impact forecast and monitoring
schedule for the next reporting month.
Section 9: Conclusions
The Organic Resources Recovery Centre (ORRC) Phase
I development (hereinafter referred to as “the Project”) is to design,
construct and operate a biological treatment facility with a capacity of about
200 tonnes per day and convert source-separated organic waste from commercial
and industrial sectors (mostly food waste) into compost and biogas through proven
biological treatment technologies.
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) Study completed in 2009.
The Director of Environmental Protection approved this EIA Report under the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) in February 2010
(Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).
Subsequent Report on Re-assessment on Environmental Implications and Report on
Re-assessment on Hazard to Life Implications were completed in 2013,
respectively.
An Environmental Permit (EP) (No. EP-395/2010) was issued
by the Environmental Protection Department (EPD) to the EPD, the Permit Holder,
on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013
(No. EP-395/2010/B), respectively. The Design Build and Operate Contract
for the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery
Centre (Phase 1) (the Contract)) was awarded to SITA Waste Services Limited,
ATAL Engineering Limited and Ros-Roca, Sociedad Anonima jointly trading as the
OSCAR Bioenergy Joint Venture (OSCAR or the Contractor). A Further EP
(No. FEP-01/395/2010/B) was issued by the EPD to the OSCAR on 16 February
2015. Variation to both EPs No. EP-395/2010/B and No. FEP-01/395/2010/B
were made in December 2015. The latest EPs, No. EP-395/2010/C and No.
FEP-01/395/2010/C, were issued by the EPD on 21 December 2015.
Under the requirements of Condition 5 of the
EP (No. FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A)
programme as set out in the Agreement No. CE7/2008 (EP) EM&A Manual
(hereinafter referred to as EM&A Manual) is required to be
implemented. ERM-Hong Kong, Ltd (ERM) has been appointed by OSCAR as the
Environmental Team (ET) to undertake the EM&A programme for the
Contract.
The construction works commenced on 21 May 2015 and
are scheduled for completion by March 2019 tentatively (construction completion
to be confirmed by OSCAR).
The Project Site is located at Siu Ho Wan in North
Lantau with an area of about 2 hectares. The layout of the Project Site is illustrated in Annex A.
A summary of the major construction activities
undertaken in the reporting period is shown in Table 2.1. The
locations of the construction activities are shown in Annex B. The construction programme of the Project is presented in Annex C.
Table 2.1
Summary of Construction Activities Undertaken in the Reporting Period
Construction Activities Undertaken |
· Systems being operated – waste reception, pre-treatment, CAPCS extraction, the digesters, the centrifuge, the desulphurization, the emergency flare, the CHPs, the ASP and the biological waste water treatment plant; · Process commissioning in progress - waste reception, pre-treatment, CAPCS extraction, the digesters, the centrifuge, the composting tunnels, the desulphurisation, the emergency flare, the CHPs, the ASP and the biological waste water treatment plant (about 110-130 t/d SSOW input). |
The project organisation chart and contact details
are shown in Annex D.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table
2.2.
Table 2.2 Summary of Environmental
Licensing, Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C
|
Throughout the Contract
|
Permit granted on 21 December 2015
|
Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00024352-2016 |
3 June 2016 – 30 June 2021 |
Approved on 3 June 2016 |
Construction Noise Permit – P1&P2 |
GW-RW0229-18 (Superseded CNP GW- RW0637-17) |
21 July 2018 - 20 January 2019 |
Approved on 19 June 2018 |
Construction Noise Permit – P1&P2 |
GW-RW0538-18 (Superseded CNP GW-RW0229-18) |
21 January 2019-20 July 2019 |
Approved on 31 December 2018 |
Construction Noise Permit – P5 (slope) |
GW-RW0347-18 (superseded the GW-RW0107-18) |
30 September 2018 – 29 March 2019 |
Approved on 15 August 2018 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
All the relevant environmental mitigation measures listed in the
approved EIA Report and EM&A Manual are summarised in Annex E.
According to the EM&A Manual and EP
requirements, no air quality, noise and water quality monitoring is required
during the construction phase.
According to the EM&A Manual and EP
requirements, odour monitoring is required during the commissioning
phase.
The odour patrols shall be conducted by an odour
patrol team. The odour patrol team will patrol and sniff along an odour patrol
route at the site boundary. The implementation of the odour patrol shall be
subject to the prevailing weather forecast condition and no odour patrol should
be carried out during rainy day. The odour patrol team should be comprised of
at least two independent trained personnel / competent persons, who should pass
a set of screening tests.
Odour patrols were conducted by representatives of
the Contractor, the ER and Employer (EPD Project Team) on 2, 4, 7, 9, 11, 14,
16, 18, 21, 24, 25, 28 and 30 January 2019. According to the EM&A
Manual and EP requirements, it is considered an exceedance if the odour
intensity recorded by the panellists is Level 2 or above. During this
reporting period, no Level 2 Odour Intensity was recorded. The odour
patrol results are shown in Annex H.
No air sample was collected during this reporting period.
Bi-weekly landscape and visual audit is required to
ensure that the design, implementation and maintenance of landscape and visual
mitigation measures recommended in the approved EIA Report are fully achieved.
The Contractor has implemented environmental
mitigation measures and requirements as stated in the approved EIA Report and
EM&A Manual. The implementation status of the measures during the
reporting period is summarised in Annex E.
Wastes generated from this Project include inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction waste). Construction waste comprises
general refuse, metals and paper/cardboard packaging materials. Metals
generated from the Project are also grouped into construction waste as the
materials were not disposed of with others at public fill. Reference has
been made to the Monthly Summary Waste Flow Table prepared by the Contractor
(see Annex F).
With reference to the relevant handling records and trip tickets of this
Project, the quantities of different types of waste generated in the reporting
month are summarised in Table 5.1.
Table 5.1
Quantities of Waste Generated from the Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste (e) |
||
January 2019 |
21.13 tonnes |
0.00 kg |
4.55 tonnes |
1,880.00 L |
Notes: (a) Inert C&D materials (public fill) include bricks, concrete, building debris, rubble and excavated spoil. In total, 21.13 tonnes of inert C&D material were generated from the Project. The detailed waste flow is presented in Annex F. (b) Non-inert C&D materials (construction wastes) include metals, paper / cardboard packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped into construction wastes as the materials were not disposed of with others at the public fill. (c) 0.00 kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent to recyclers for recycling during the reporting period. (d) Construction wastes other than metals, paper/cardboard packaging, plastics and chemicals were disposed of at NENT Landfill by subcontractors. (e) 1,880.00 L of chemical waste was collected by licenced waste collector. |
Joint site inspections were conducted by
representatives of the Contractor, the ER, IC and the ET on 2, 8, 17 and 25
January 2019. The IEC was also present at the joint inspection on 17
January 2019. Follow-up actions resulting from the last site inspections
were generally taken as reported by the Contractor.
Key observations during the reporting period are
summarised as follows:
2 January 2019
· No particular observation during this site inspection.
8 January 2019
· Open stockpile was observed near second access and the contractor was
advised to cover the stockpile properly with tarpaulin if the stockpile is
placed overnight to avoid dust emission.
· Chemical drums were observed near Building 2 and the contractor was
advised to provide drip trays to the chemical drums or replace the drums to
designed storage area according to the Code of Practice.
· Construction parts were observed next to Building 2 and the contractor
was advised to remove or store the parts properly to avoid stockpile of parts
outdoor.
17 January 2019
· Open stockpile was observed near second access and the contractor was
advised to cover the stockpile properly with tarpaulin if the stockpile is
placed overnight to avoid dust emission.
· Chemical drums were observed near Building 2 and the contractor was
advised to provide drip trays to the chemical drums or replace the drums to
designed storage area according to the Code of Practice.
· Construction parts were observed next to Building 2 and the contractor
was advised to remove or store the parts properly to avoid stockpile of parts
outdoor.
25 January 2019
·
Open stockpile was observed near second
access and the contractor was advised to cover the stockpile properly with
tarpaulin if the stockpile is placed overnight to avoid dust emission.
·
Chemical drums were observed near Building 2
and the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
·
Construction parts were observed next to
Building 2 and the contractor was advised to remove or store the parts properly
to avoid stockpile of parts outdoor.
In accordance with the EM&A Manual, bi-weekly landscape and visual
inspection is required to ensure that the design, implementation and
maintenance of landscape and visual mitigation measures recommended in the EIA
Report are fully achieved. On-site inspections of the landscape and
visual mitigation measures were performed on 8 and 25 January 2019.
It was confirmed that the necessary landscape
and visual mitigation measures as summarised in Annex E were
generally implemented by the Contractor. No specific
observation was found during site inspections on 8 and 25 January 2019.
No non-compliance event was received during the
reporting period.
Works to be undertaken for the coming reporting
period are summarised in Table 8.1.
Table 8.1
Construction Works to be undertaken in the Next Reporting Period
Construction Activities Undertaken |
· Continue the testing and process commissioning works. |
Only testing and process commissioning works are
expected in the next reporting period. No construction activities have been
scheduled in February 2019 and hence no potential environmental impacts are
expected.
The most up-to-date construction programme for the
Project is presented in Annex C.
This EM&A Report presents the EM&A
programme undertaken during the reporting period from 1 to 31 January 2019 in
accordance with EM&A Manual and requirements of EP
(FEP-01/395/2010/C).
No air quality, noise and water quality monitoring
is required during the construction phase.
Odour patrols and monitoring are required during
the commissioning phase. No exceedance of odour intensity limit for all
odour patrol events. No air sample was collected during this reporting
period.
Bi-weekly landscape and visual monitoring was
conducted in the reporting period. The necessary landscape and visual
mitigation measures recommended in the approved EIA Report were generally
implemented by the Contractor.
No incident occurred during reporting period.
No complaint/summon/prosecution was received.